Data Centers & Energy
Behind-the-meter power is onsite generation used before the utility meter. See why data centers are going BTM, the options, the new rules and the tax credits.
Author -
Paulestini Francois
Published -
READ TIME
A new data center can be built in about two years. Getting power from the grid can take three to seven. That gap is pushing the biggest power users in America to build their own electricity on site, behind the utility meter. Here's what behind-the-meter power is, how it differs from front-of-the-meter power, why data centers are using it, the rules taking shape and the tax credits that can help pay for it.
QUICK ANSWER
Behind-the-meter (BTM) power is electricity generated or stored on the customer's side of the utility meter, such as rooftop solar, batteries, fuel cells or onsite gas turbines, and used on site without flowing through the grid first. Data centers are turning to it because grid connections can take 3 to 7 years.
KEY FACTS
What does BTM mean in energy? Behind the meter: generation or storage on the customer's side of the utility meter, used on site.
What is front-of-the-meter power? Grid-connected assets such as power plants, utility-scale solar farms and transmission lines that sell into the grid.
Why do data centers use behind-the-meter power? Grid connections can take 3 to 7 years, while a data center can be built in 18 to 24 months.
How long is the grid interconnection wait? The median power project built in 2025 took 61 months from request to operation, per Berkeley Lab.
What is co-location? Building a large load, like a data center, right next to a power plant so it can draw power directly.
Does behind-the-meter power get the investment tax credit (ITC)? Fuel cells, solar and battery storage can earn a 30% ITC; natural gas turbines don't qualify.
Can BTM projects get the production tax credit (PTC)? Yes, under 45Y, if an unrelated party owns and operates the meter measuring on-site use.
What is behind-the-meter power?
Behind-the-meter (BTM) power is electricity generated or stored on the customer's side of the utility meter, so it's used on site without flowing through the public grid first. Rooftop solar, batteries, fuel cells and onsite gas turbines at a factory or data center are all behind-the-meter power.
The meter is the dividing line. Everything on the grid side of it, including power plants, transmission lines and substations, is "in front of the meter," EnergySage explains. Anything on your side of it, owned by you or a partner, is behind it.
People often write it without hyphens, as behind the meter power or BTM power, but it means the same thing. For a home, that might mean solar panels and a battery. For a data center, it can mean hundreds of megawatts of onsite generation built to run the facility directly. That second use is why searches for behind-the-meter power have jumped in 2026.
What is the difference between behind-the-meter and front-of-the-meter?
Behind-the-meter systems sit on the customer's property and serve its own load. Front-of-the-meter systems, like utility-scale solar farms and power plants, connect to the grid and sell power into it. The difference is where the asset connects and who uses the electricity.

The distinction matters for money and rules. A front-of-the-meter project needs a grid interconnection agreement and sells into wholesale markets. A behind-the-meter project mainly avoids buying power, cuts demand charges and keeps a site running if the grid goes down. Our guide to commercial electricity rates shows what onsite power can offset.
Some arrangements blur the line. A data center built right next to a power plant, called co-location, may draw power directly from the plant while still touching the grid. Regulators are now writing rules for exactly those setups.
Why are data centers going behind the meter?
Data centers are going behind the meter because the grid can't connect them fast enough. A data center can be built in 18 to 24 months, but getting grid power can take 3 to 7 years in many markets. Onsite generation lets operators turn on years sooner.
That gap comes from datacenterHawk's February 2026 analysis, which found new requests now routinely arrive at 100 MW to 500 MW or more. North America absorbed nearly 15,600 MW of data center capacity in 2025 alone. The power plant side of the queue is also slow: the median project built in 2025 took 61 months from interconnection request to operation, up from 22 months in 2008, according to Lawrence Berkeley National Laboratory.

The money is enormous. Meta, Google, Amazon Web Services and Microsoft plan $635 billion to $660 billion of data center spending in 2026, and about one-third of new data center projects intend to rely on behind-the-meter energy, citing Bloom Energy and Cleanview, Uptime Intelligence reported. Use the interactive chart below to see how grid wait times have grown.
Power plants that came online in 2025 waited a median of 61 months from their interconnection request to commercial operation. The dashed line marks roughly how long it takes to build a data center.
Source: Lawrence Berkeley National Laboratory, Queued Up (2025 and 2026 editions). Figures are for power plants seeking grid connection.
What types of behind-the-meter power do data centers use?
Data centers use four main kinds of behind-the-meter power: natural gas turbines and engines, fuel cells, solar paired with batteries, and co-location next to existing power plants such as nuclear. Many use onsite power as a bridge until the grid connection arrives.
Natural gas turbines and engines. Williams is building Socrates North and South in New Albany, Ohio, two 200 MW natural gas plants for a combined 400 MW, targeted for service in 2026, according to Williams.
Fuel cells. Fuel cells can be installed in modular blocks and scaled quickly. See our guide to data center fuel cell costs.
Solar plus storage. On-site solar and batteries cut daytime grid use and add backup.
Co-location. Talen Energy's data center at the Susquehanna nuclear plant in Pennsylvania is a well-known example.

The Foley 2026 Data Center Survey found 56% of developers are exploring co-located or onsite generation. In grid operator rules, onsite plants like these are often called behind the meter generation. Our comparison of natural gas vs. hydrogen fuel cells for data centers covers the fuel choice.
What are the rules for behind-the-meter power?
The rules are being written now. On December 18, 2025, the Federal Energy Regulatory Commission (FERC) ordered PJM, the largest U.S. grid operator, to create new transmission services for data centers co-located with power plants, and found PJM's behind-the-meter generation rules could shift costs onto other customers.
The order directs PJM to offer options such as firm and non-firm contract demand service for co-located loads, Foley & Lardner explains. FERC left the bigger question of who regulates large-load interconnection to a separate proceeding, so state utility laws still matter.
Congress is weighing in too. The Senate's permitting reform bill would bar utilities from charging other customers for grid upgrades a data center causes. Critics, including Sen. Jeff Merkley, warn it could also make it easier to build data centers powered by behind-the-meter gas plants.
Do behind-the-meter systems qualify for tax credits?
Yes, if they use qualifying clean technology. Fuel cells can earn a 30% investment tax credit (ITC), and solar and battery storage can claim the 30% Section 48E ITC with prevailing wage. Natural gas turbines and engines don't qualify for clean energy credits.
The production tax credit (PTC) works differently. Section 45Y normally requires power to be sold to an unrelated person, but it also counts electricity the owner uses or stores on site if the facility has a meter owned and operated by an unrelated person, under 26 U.S.C. 45Y. That makes behind-the-meter projects eligible for either credit when they're set up correctly.
Credits can be sold for cash under Section 6418, which helps fund the system. Our guides to the fuel cell tax credit and battery storage tax credit cover eligibility. Use the calculator below to compare going behind the meter with waiting for the grid.
Building 100 MW of onsite fuel cells in 18 months instead of waiting 48 months for the grid lets the data center run 30 months sooner, worth about $450.0M at your revenue rate. Paying $40/MWh more for power over that bridge costs about $70.1M, and the 30% investment tax credit on the $300.0M system is worth about $82.8M if sold.
Illustrative estimate. Bridge energy assumes an 80% average load. Wait times, build times, revenue, costs and credit eligibility (including prevailing wage and prohibited foreign entity rules) are your own assumptions; confirm with your utility and tax advisor. Not tax or investment advice.
What are the pros and cons of behind-the-meter power?
The biggest advantages are speed, reliability and control over energy costs. The drawbacks are high up-front cost, the need to run and fuel your own power plant, permitting and air-quality rules for onsite generation, and regulatory uncertainty about how co-located loads share grid costs.
Pro: speed to power. Onsite generation can be built far faster than a new grid connection.
Pro: resilience. A site with its own power can keep running during grid outages.
Con: cost and operations. You own the plant, the fuel contracts and the maintenance.
Con: policy risk. Rules on co-location, backup service and cost allocation are still changing.
How do you decide between behind-the-meter power and the grid?
Compare how long the grid connection will take, what each month of delay costs you, what onsite power costs to build and run, and which tax credits apply. If the grid is years away and your load earns a lot per month, a behind the meter data center setup often wins, at least as a bridge.
Start with your utility. Ask for a written timeline and cost estimate for the grid connection and any upgrades you'd have to pay for. Then price onsite options with real quotes, not rules of thumb, because equipment lead times and fuel costs vary widely by region.
Time. How many months sooner can onsite power run the site?
Revenue. What does each month of operation earn or save?
Energy cost. How much more does onsite power cost per megawatt-hour than grid power?
Credits. Will a fuel cell, solar or storage system earn a 30% credit you can sell?
Exit plan. Will the onsite system keep running as backup once the grid arrives, or be moved or sold?
If you plan to sell the credit, line up a buyer early. Our guide to transferable tax credit pricing shows what buyers pay today.
Is behind-the-meter power here to stay?
For data centers, very likely. As long as grid connections take years and AI demand keeps climbing, operators will keep building their own power, at least as a bridge. Some markets now ask developers to show an independent power plan before approving new data centers.
Over time, many sites may run hybrid setups: onsite power for speed and resilience, plus a grid connection once it's available. Clean behind-the-meter options like fuel cells, solar and batteries carry tax credits that gas doesn't, which can tip the economics. For the bigger picture on pooled distributed energy, see our guide to virtual power plants.
Sources
Lawrence Berkeley National Laboratory, Queued Up: 2026 Edition
Uptime Intelligence, Regulations for behind-the-meter power are emerging (February 25, 2026)
Foley & Lardner, FERC Opens New Paths for Co-Located Loads in PJM (December 2025)
EnergySage, Behind-the-Meter: What You Need to Know (updated August 2026)
26 U.S.C. 45Y, Clean electricity production credit (Cornell LII)
Utility Dive, Permitting bill advances in Senate (November 10, 2026)
Frequently Asked Questions
Is behind-the-meter solar worth it for a business?
Often, yes. On-site solar cuts the power a business buys from the grid, can lower demand charges when paired with batteries and may qualify for a 30% investment tax credit. The payback depends on your electricity rates, roof or land space and how much power you use during sunny hours.
Can behind-the-meter power sell electricity back to the grid?
Is behind-the-meter gas power clean energy?
What did FERC decide about co-located data centers?
Can Cenet Capital help fund behind-the-meter power?
Bringing your own power?
Cenet Capital helps data center developers and large energy users value the investment tax credit on onsite fuel cells, solar and battery storage, and sell those credits to corporate buyers for cash to help fund behind-the-meter power. Share your project size, location and timeline, and we'll show you what your credits could bring in.