Palisades Nuclear: The Shut-Down Plant That Came Back (and the Tax Credits Behind It)

Palisades Nuclear: The Shut-Down Plant That Came Back (and the Tax Credits Behind It)

Palisades nuclear plant is the first U.S. reactor to return from decommissioning. See the restart date, who's paying and the 45Y tax credit it can earn.

Author -

Paulestini Francois

Published -

READ TIME

7 min read

In 2022, the Palisades nuclear plant in Michigan shut down and was sold to a company whose job was to take it apart. Four years later, it's on the edge of becoming the first retired U.S. nuclear plant ever to run again. Here's what Palisades is, why it closed, when it will restart, who's paying for it and how a little-known tax rule treats the restart as a brand-new power plant.

QUICK ANSWER

The Palisades nuclear plant is an 800-megawatt reactor in Covert Township, Michigan, that closed in May 2022 and is being restarted by Holtec International. As of mid-November 2026, the restart was targeted for the end of 2026, backed by a $1.52 billion DOE loan, $300 million from Michigan and 45Y tax credits.

KEY FACTS

  • Who owns the Palisades nuclear plant? Holtec International, through Holtec Palisades, which bought it from Entergy in June 2022.

  • Where is Palisades? On the Lake Michigan shore in Covert Township, Van Buren County, Michigan, near South Haven.

  • How big is Palisades? About 800 megawatts, enough to power more than half a million average U.S. homes.

  • Who buys Palisades power? Wolverine Power Cooperative and Hoosier Energy, under PPAs with an initial 28-year term.

  • Is Palisades the first nuclear plant restart? Yes. It would be the first U.S. plant to return from decommissioning, ahead of Crane (Three Mile Island) and Duane Arnold.

  • Does Palisades get the 45U or 45Y production tax credit (PTC)? The 45Y credit, because a qualifying restart is treated as new capacity. 45U is for existing reactors.

  • Can the Palisades restart credits be sold? Yes. Under Section 6418, an owner can transfer 45Y credits to corporate buyers for cash.

What is the Palisades nuclear plant?

The Palisades Nuclear Generating Station is an 800-megawatt pressurized water reactor on Lake Michigan in Covert Township, Michigan. It started producing power at the end of 1971 and closed in May 2022. Holtec International bought it to tear it down, then reversed course and is now bringing it back online.

If the restart succeeds, Palisades will be the first U.S. nuclear plant ever to return from decommissioning. The U.S. Department of Energy says the repowered plant could supply firm baseload power until at least 2051, subject to Nuclear Regulatory Commission (NRC) licensing. Its current operating license runs to 2031.

Size matters here. A plant this big running most hours of the year makes about as much electricity in a year as more than half a million American homes use, and it emits no carbon while doing it. That's why the Palisades nuclear restart has drawn support from two administrations, Michigan and two rural cooperatives, plus heavy criticism from anti-nuclear groups.

Why did the Palisades nuclear plant close?

Palisades closed on May 20, 2022, because its owner at the time, Entergy, decided the plant was no longer worth running. Entergy had agreed in 2018 to sell it to Holtec for decommissioning, and the sale closed in June 2022. The NRC lists the plant as having permanently ceased operations after more than 40 years.

The closure fit a pattern. Through the 2010s, cheap natural gas and flat power demand pushed several older U.S. reactors into early retirement. Palisades was licensed to run until 2031, so it shut down with years of licensed life left, according to the NRC.

Then the market flipped. Power demand from data centers, manufacturing and electrification started climbing, and federal policy swung toward keeping clean, always-on power plants running. Holtec began the NRC reauthorization process in October 2023.

Palisades nuclear plant timeline: begins producing power in 1971, Entergy shuts it down in May 2022, $1.52 billion DOE loan closes in September 2024, returns to operating status in August 2025, restart target late 2026, PPA in-service deadline March 2027. An 800 MW reactor on Lake Michigan in Covert Township, Michigan.

When will Palisades restart?

Palisades had not restarted as of mid-November 2026. Energy Secretary Chris Wright said on October 29, 2026, that it could restart by the end of November and would be running before the end of the year. Once the NRC clears it, Holtec says power will ramp up over several weeks.

The date has slipped more than once. Holtec first aimed for late 2025, then pushed the restart into 2026, Michigan Public reported. The NRC approved Holtec's licensing package in July 2025, and on August 25, 2025, the plant officially moved from decommissioning status back to operating status for regulatory purposes, according to Holtec's IPO filing.

The latest delay came during fuel loading. In late summer 2026, a fuel assembly tilted while crews were lowering it into the reactor, which paused the work. The NRC said no radiation was released. Holtec retrieved the assembly and reloaded fuel in October, and Wright said after touring the plant that "it is very close."

There's also a hard deadline. Holtec's filing says its power purchase agreements require the plant to be in service by March 2027, or either side can terminate, with up to $100 million in termination payments at stake.

DOE loan
$1.52B
$3.1Bpublic supportDOE loan$1.52BUSDA grants$1.32BMichigan$0.30B

DOE loan of up to $1.52 billion, closed September 2024, the first under the Energy Infrastructure Reinvestment program. That's 48% of the roughly $3.1 billion in public support.

Sources: U.S. DOE loan project page; World Nuclear News (2024); Holtec Nuclear Corp Form S-1/A (September 2026). Holtec also invests its own capital, which isn't shown.

Who is paying for the Palisades restart?

Federal and state money carries much of the cost. The DOE closed a loan of up to $1.52 billion in September 2024, Michigan approved $300 million, and the USDA awarded about $1.3 billion in grants to the two cooperatives buying the power. Holtec covers the rest with its own capital.

The DOE loan was the first closing under the Energy Infrastructure Reinvestment program, which finances projects that put retired energy infrastructure back to work, World Nuclear News reported. The USDA grants went to Wolverine Power Cooperative (more than $650 million) and Hoosier Energy ($675 million) to help them buy Palisades power.

Those two cooperatives signed power purchase agreements for the full output. Wolverine takes about two-thirds and Hoosier takes the rest, under contracts with an initial term of 28 years. That long, fixed buyer contract is what made the debt possible. Our guide to offtake agreements explains why lenders want one before they fund.

A rural road through farm fields leading to a nuclear power plant and its cooling towers

What tax credits does the Palisades restart get?

A restarted nuclear plant like Palisades can qualify for the Section 45Y clean electricity production tax credit (PTC) as if it were a brand-new plant. In 2026, that credit is worth up to 3.1 cents per kilowatt-hour for 10 years if prevailing wage and apprenticeship rules are met, or 0.6 cents if they aren't.

The rule that makes this work is in the final 45Y regulations, 26 CFR 1.45Y-4(c)(3). A decommissioned plant that restarts can count its capacity as new, "from a base of zero," if four conditions hold:

  • The plant ceased operations.

  • It was shut down for at least one calendar year without authorization to operate from the NRC or FERC.

  • It restarts under an operating license issued by the NRC or FERC.

  • It didn't shut down just to qualify for this rule.

How a restarted nuclear plant qualifies for the 45Y credit: 1, the plant ceased operations; 2, it was shut down at least one calendar year without NRC authorization; 3, it restarts under an NRC or FERC license; 4, it did not shut down just to qualify. It is treated as new capacity worth 3.1 cents per kWh for 10 years at the 2026 rate with prevailing wage. Source: 26 CFR 1.45Y-4(c)(3) and IRS Notice 2026-47.

The regulation's own example is a hypothetical 800-megawatt nuclear plant that closes, restarts and gets a fresh 10-year credit period. The 2026 rates come from IRS Notice 2026-47, published in IRB 2026-41.

That's a different credit from the Section 45U nuclear production tax credit for existing reactors, which shrinks as a plant's power revenue rises. Canary Media corrected its own reporting to say Palisades qualifies for 45Y, not 45U. Our Section 45Y guide covers the general rules.

45Y credits per year
$195.5MFull rate
Credits over 10 years$1.96B
Cash if sold at 93 cents$1.82B
Discount kept by the buyer$136.9M
Output per year6.31M MWh
Homes' worth of power584K
Credit per MWh$31

At 800 MW and a 90% capacity factor, the plant makes about 6.31 million MWh a year. At 3.1 cents per kWh, that's $195.5M in 45Y credits a year and $1.96B over 10 years. Sold at 93 cents on the dollar, the credits would bring in about $1.82B.

Illustrative estimate at the flat 2026 rate (IRS Notice 2026-47). Real credits depend on actual output, outages, annual inflation adjustments and IRS eligibility, including foreign entity rules. Homes use 10,791 kWh a year (EIA average). Not tax advice.

How much could Palisades earn in 45Y credits?

By our estimate, roughly $200 million a year. An 800 MW plant running at a 90% capacity factor makes about 6.3 million megawatt-hours a year, and at $31 per MWh that's about $196 million in credits, or close to $2 billion over the 10-year credit period, before inflation adjustments.

This is our math, not a Holtec disclosure. Holtec's filing says only that it benefits from production tax credits for qualifying nuclear projects and that how the rules apply "is subject to a number of uncertainties." Real output depends on the ramp-up, refueling outages every 18 months and how a 50-year-old plant runs after four idle years.

The credit is also transferable. Under Section 6418, an owner can sell 45Y credits to unrelated corporate taxpayers for cash. Buyers typically pay a little under face value, as our guide to transferable tax credit pricing explains. Use the calculator below to change the capacity, run rate and sale price.

Is restarting Palisades safe?

The NRC approved the restart and says it will keep verifying safety requirements before and after power operations. Critics disagree. Advocacy groups sued Holtec and the NRC in November 2025 to block the restart, and the NRC flagged work environment concerns at the plant in October 2026.

Groups like Beyond Nuclear and Don't Waste Michigan argue the plant's steam generators and other aging equipment weren't maintained while it sat idle. Kevin Kamps of Don't Waste Michigan called the restart "radioactive Russian roulette." The tilted fuel assembly in 2026 strengthened that argument, even though no radiation escaped.

Supporters point to the inspection and repair work done since 2023, the NRC's review and the up to 650 jobs the DOE expects the plant to support or retain. Federal law also covers accident liability through the Price-Anderson Act's industry-wide insurance pool.

What other nuclear plants are restarting?

Two more retired plants are working to follow Palisades: the Crane Clean Energy Center, formerly Three Mile Island Unit 1, in Pennsylvania, and the Duane Arnold Energy Center in Iowa. Both are backed by tech company power contracts, and the DOE is lending as much as $4.4 billion across the three restarts.

Constellation's Crane restart is tied to a 20-year power purchase agreement with Microsoft. NextEra's Duane Arnold restart will bring 615 megawatts back to the grid under a 25-year agreement with Google, backed by a DOE loan of up to $1.9 billion, and is now targeted for early 2029, POWER Magazine reported.

Holtec also plans two new SMR-300 small modular reactors, called Pioneer One and Two, at the Palisades site. It filed the first part of a construction permit application on December 31, 2025, and signed a framework agreement with a hyperscale data center company for up to 680 MW. For the bigger picture on how data center demand is changing power deals, see our guide to data center fuel cell costs.

Sources

Frequently Asked Questions

Is the Palisades nuclear plant running now?

Not as of mid-November 2026. Energy Secretary Chris Wright said on October 29, 2026, that it could restart by the end of November and would be running before year-end. After NRC clearance, Holtec says power ramps up over several weeks.

What happened at Palisades during fuel loading?

How long will Palisades run after it restarts?

Are other nuclear plants restarting?

Can Cenet Capital help me sell clean energy tax credits?

Selling nuclear or clean power credits?

Cenet Capital helps owners of nuclear, solar, storage and other clean power projects value their Section 45Y and 48E credits, check eligibility and timing rules and sell the credits to corporate buyers for cash. Share your project size, location and timeline, and we'll show you what your credits could bring in.

Interested in selling your clean energy tax credits?

  • More Insights

Cenet Capital was founded in on a simple premise: public markets price in consensus faster than they price in research. A small team built a trading book around that idea concentrated, thesis-driven, willing to be early.

Follow Us:

Cenet Capital was founded in on a simple premise: public markets price in consensus faster than they price in research. A small team built a trading book around that idea concentrated, thesis-driven, willing to be early.

Follow Us:

Cenet Capital was founded in on a simple premise: public markets price in consensus faster than they price in research. A small team built a trading book around that idea concentrated, thesis-driven, willing to be early.

Follow Us: