San Onofre Is Being Demolished While Other Nuclear Plants Come Back From the Dead. Why?

San Onofre Is Being Demolished While Other Nuclear Plants Come Back From the Dead. Why?

The San Onofre nuclear power plant's domes come down by 2027 as Palisades and Three Mile Island restart. Why SONGS can't, what it costs, where the waste goes.

Author -

Paulestini Francois

Published -

READ TIME

7 min read

Michigan is restarting a dead nuclear plant. Pennsylvania is bringing back Three Mile Island. Iowa is reviving Duane Arnold for Google. And in Southern California, crews are about to knock down the famous domes of the San Onofre nuclear power plant for good. Here's what's happening at San Onofre, why it shut down, why it can't come back like the others, what the teardown costs, where its nuclear waste goes and how federal tax credits now reward plants that stay alive.

QUICK ANSWER

The San Onofre nuclear power plant (SONGS) in Southern California is being demolished. Rep. Mike Levin says its twin domes will come down by the end of 2027. It closed in 2013 after a steam generator failure and can't be restarted, but about 1,600 tons of spent fuel remain on site.

KEY FACTS

  • Is San Onofre being torn down? Yes. 52 of 62 structures are already gone, and the domes are due to be demolished by the end of 2027.

  • When did San Onofre shut down? Units 2 and 3 went offline in January 2012 and were permanently retired in June 2013.

  • Why did San Onofre close? Its new Mitsubishi steam generators failed, and Unit 3 leaked radioactive steam on January 31, 2012.

  • How much spent nuclear fuel is at San Onofre? About 1,600 metric tons, sealed in 123 steel canisters roughly 100 feet from the ocean.

  • How much does decommissioning San Onofre cost? About $4.94 billion, based on estimates California regulators found reasonable.

  • Is Diablo Canyon still running? Yes. California's last nuclear plant can run through 2030; its NRC licenses now reach 2044 and 2045, pending state approval.

  • What tax credit does a nuclear restart get? The 45Y production tax credit (PTC), worth 3.1 cents per kWh in 2026 for 10 years; operating plants get 45U.

What is happening to the San Onofre nuclear power plant?

The San Onofre nuclear power plant is being torn down. Rep. Mike Levin said on October 28, 2026 that crews will start demolishing its two famous containment domes in the coming months and finish by the end of 2027. Federal officials expect the whole site to be decommissioned by the end of 2028.

San Onofre: 60 years from power plant to rubble. 1968, Unit 1 starts up; 1983-84, Units 2 and 3 start up; 1992, Unit 1 shuts down; 2012, steam generator leak; 2013, plant retired for good; 2020, all fuel moved to dry storage; 2027, domes demolished; 2028, site decommissioning complete.

The San Onofre Nuclear Generating Station (SONGS) sits on the coast between San Clemente and Camp Pendleton in San Diego County. According to KTLA, 52 of the site's 62 structures have already been demolished and more than 700 million pounds of material removed.

What won't be leaving soon is the nuclear waste. Roughly 1,600 metric tons of spent fuel remain on site in steel canisters, and no permanent federal home exists for it yet. That gap, along with a wave of nuclear plant restart deals elsewhere in the U.S., is why the San Onofre demolition is getting so much attention.

Why did San Onofre shut down?

San Onofre shut down because its new steam generators failed. Unit 3 leaked radioactive steam on January 31, 2012, and inspections found rapid tube wear in both units' Mitsubishi-built replacement generators. On June 7, 2013, Southern California Edison announced it would retire Units 2 and 3 for good rather than fix them.

Edison had just finished a $671 million project in 2011 to replace the steam generators in both reactors. The leak released radiation below allowable limits, but investigators found that the new tubes were vibrating and wearing far faster than expected. Facing a long, uncertain repair, Edison chose to close the plant, according to the SONGS decommissioning timeline.

The plant had three units. Unit 1 ran from 1968 until 1992. Units 2 and 3, rated at 1,070 and 1,080 megawatts (MW) net, came online in 1983 and 1984. Edison owns about 78% of the plant, San Diego Gas & Electric 20% and the City of Riverside about 2%. An international arbitration panel later ordered Mitsubishi Heavy Industries to pay $125 million, the cap in its contract, far below the $7.57 billion Edison sought.

Why can't San Onofre be restarted like Palisades?

San Onofre can't restart because it has been dismantled. Its reactors were retired in 2013, its fuel moved to dry storage by 2020, and most buildings are gone. Palisades in Michigan closed in working order in 2022, and a new owner bought it specifically to restart it.

Why Palisades can restart but San Onofre can't. San Onofre in California: shut in 2013 after a steam generator failure, dismantling since 2020, 52 of 62 structures already gone, about 1,600 tons of spent fuel on site. Palisades in Michigan: shut in 2022 in working order, bought by a company that wanted to restart it, federal loan of up to $1.52 billion, fuel reloaded in 2026.

A nuclear restart only works when the reactor, turbine and safety systems are still there to repair. Holtec bought Palisades soon after it closed, kept its license path alive and won a federal loan of up to $1.52 billion. Our guide to the Palisades nuclear restart covers that comeback in detail. Constellation is restarting Three Mile Island Unit 1 as the Crane Clean Energy Center for Microsoft, and NextEra plans to bring back Iowa's Duane Arnold for Google around 2029 with a $1.9 billion federal loan.

San Onofre had a failed major component, an owner that chose to exit, and a decommissioning plan approved and underway for six years. Once containment structures and reactor internals are cut apart and shipped away, there's nothing left to restart. The chart below compares the plants being torn down, extended and brought back.

San Onofre net capacity
2,150 MWBeing demolished
05001,0001,5002,0002,5002,150San Onofre2,240Diablo Canyon800Palisades835Crane (TMI-1)615Duane ArnoldNet capacity, megawatts

San Onofre's Units 2 and 3 could generate about 2,150 MW combined. They shut in 2012 after a steam generator leak, retired in 2013 and are now being demolished, with the domes due to come down by the end of 2027.

Sources: Southern California Edison and CPUC (San Onofre); ANS / NRC (Diablo Canyon, April 2026); U.S. DOE and Holtec (Palisades); Constellation (Crane); NextEra (Duane Arnold). Capacities are approximate net ratings.

How much does it cost to tear down San Onofre?

Tearing down San Onofre is expected to cost about $4.94 billion. California regulators found decommissioning estimates of $225.9 million for Unit 1 and $4.712 billion for Units 2 and 3 reasonable. The money comes from decommissioning trust funds that customers paid into while the plant ran.

According to a California Public Utilities Commission fact sheet, the CPUC's August 2024 decision kept annual customer contributions to the trusts at $0 and made shareholders, not customers, cover $30 million in disallowed costs. In their December 2024 filing, Edison and SDG&E asked regulators to approve about $524 million of San Onofre decommissioning work completed from 2021 to 2023.

That price tag is part of why restarts look attractive elsewhere. For less than a third of what it costs to take San Onofre apart, a federal loan is helping put Palisades' 800 MW of carbon-free power back on the grid.

What happens to San Onofre's nuclear waste?

San Onofre's spent nuclear fuel, about 1,600 metric tons, will stay on site in 123 sealed steel canisters until the federal government takes it. Rep. Levin's Spent Fuel Prioritization Act would move high-risk sites like San Onofre to the front of the line for removal.

The spent fuel pool inside the San Onofre Nuclear Generating Station in 2014, glowing blue-green under bright lights before the fuel moved to dry storage

All of the fuel was moved from cooling pools into dry storage by August 2020. Edison says 50 canisters sit in an older horizontal storage system and 73 in a newer Holtec system, according to its spent fuel storage page.

According to CalMatters, Levin's bill is waiting in the House Energy and Commerce Committee, and it would favor sites with high seismic hazards, large nearby populations and national security risks. Utah, Tennessee, Oklahoma, Louisiana and Idaho have signed agreements with the Department of Energy to explore hosting "Nuclear Lifecycle Innovation Campuses" for spent fuel. Levin said such sites could start operating by the late 2030s.

What did California lose when San Onofre closed?

California lost about 2,150 MW of carbon-free, around-the-clock power when San Onofre's two big units closed. That leaves Diablo Canyon as the state's last nuclear plant, with 2,240 MW supplying nearly 9% of California's electricity, and its future past 2030 depends on the Legislature.

After the 2013 closure, the gap was filled largely by new natural gas plants plus some energy storage, according to the plant's history. Diablo Canyon was itself slated to close in 2024 and 2025 until a 2022 state law kept it open through 2030. On April 2, 2026, the Nuclear Regulatory Commission renewed Diablo Canyon's licenses to 2044 and 2045, but the plant can only use them if lawmakers agree, the American Nuclear Society reports.

The stakes are rising as data centers drive up power demand and commercial electricity rates climb. Losing another 2,240 MW of firm power would be much harder to replace than solar output alone, which is why some tech companies are now buying nuclear power directly or building behind-the-meter power.

How do tax credits make nuclear restarts pay off?

A restarted reactor can qualify for the Section 45Y clean electricity production tax credit (PTC) as if it were new, worth 3.1 cents per kWh in 2026 with prevailing wage met, for 10 years. Operating plants get the smaller Section 45U nuclear credit instead. Both credits can be sold for cash.

Treasury's 45Y rules let a plant that was shut for at least one calendar year count its restored capacity "from a base of zero," so it's treated as a new facility for the full 10-year credit. Existing reactors instead claim the 45U nuclear production tax credit, which phases down as power prices rise and ends after 2032. Our explainer on the 45Y tax credit covers the restart rule.

The math is big. A single 1,070 MW unit like one of San Onofre's, running 90% of the time, would make about 8.4 billion kWh a year. At 3.1 cents, that's roughly $260 million in credits annually, which an owner could sell to corporate buyers for about 93 cents on the dollar. Try your own plant size in the calculator below.

45Y credits per year
$195.5MFull rate
Credits over 10 years$1.96B
Cash if sold at 93 cents$1.82B
Discount kept by the buyer$136.9M
Output per year6.31M MWh
Homes' worth of power584K
Credit per MWh$31

At 800 MW and a 90% capacity factor, the plant makes about 6.31 million MWh a year. At 3.1 cents per kWh, that's $195.5M in 45Y credits a year and $1.96B over 10 years. Sold at 93 cents on the dollar, the credits would bring in about $1.82B.

Illustrative estimate at the flat 2026 rate (IRS Notice 2026-47). Real credits depend on actual output, outages, annual inflation adjustments and IRS eligibility, including foreign entity rules. Homes use 10,791 kWh a year (EIA average). Not tax advice.

Could California build or restart nuclear power again?

Not at San Onofre. California law still bars new nuclear plants until there's a federal solution for spent fuel, though some lawmakers want to lift that moratorium. The realistic near-term choice is whether to keep Diablo Canyon running past 2030.

That decision matters well beyond California. Every reactor that keeps running avoids a teardown bill like San Onofre's, keeps carbon-free power on the grid and can earn federal tax credits that are worth hundreds of millions of dollars a year. For developers of nuclear, geothermal or other firm clean power, the lesson from San Onofre is simple: the economics of keeping a plant alive now look far better than they did in 2013.

Sources

Frequently Asked Questions

Can you still see the San Onofre domes?

Yes, for now. The domes are still standing next to San Onofre State Beach and I-5, but Rep. Mike Levin says crews will start demolishing them in the coming months and finish by the end of 2027.

Is San Onofre dangerous?

Who owns San Onofre?

How many nuclear plants are left in California?

Can Cenet Capital help monetize nuclear tax credits?

Developing firm clean power?

Nuclear restarts, uprates and other firm clean power projects can earn hundreds of millions of dollars in federal production tax credits. Cenet Capital helps owners value 45Y and 45U credits and sell them to corporate buyers for cash. Share your project and timeline, and we'll show you what your credits could bring in.

Interested in selling your clean energy tax credits?

  • More Insights

Cenet Capital was founded in on a simple premise: public markets price in consensus faster than they price in research. A small team built a trading book around that idea concentrated, thesis-driven, willing to be early.

Follow Us:

Cenet Capital was founded in on a simple premise: public markets price in consensus faster than they price in research. A small team built a trading book around that idea concentrated, thesis-driven, willing to be early.

Follow Us:

Cenet Capital was founded in on a simple premise: public markets price in consensus faster than they price in research. A small team built a trading book around that idea concentrated, thesis-driven, willing to be early.

Follow Us: