Storage developers have spent two years racing the clock on tax credits. Now a different clock is running. Under the foreign entity of concern (FEOC) rules, a battery project that begins construction in 2026 must get at least 55% of its equipment cost from suppliers that are not prohibited foreign entities, or it does not qualify for the 30% Section 48E credit at all.

That threshold climbs every year, to 75% for projects that begin construction in 2030 and later. The US just installed a record 18.9 GWh of storage in a single quarter, so a lot of money now rides on a ratio most buyers have never calculated. This guide shows how the test works, what counts toward it, and how to run your own numbers with the calculator in this article.

QUICK ANSWER

A battery storage project that begins construction in 2026 must get at least 55% of its equipment cost from suppliers that are not prohibited foreign entities, or it loses the 30% Section 48E tax credit. The minimum rises to 75% by 2030. The test is (total direct cost minus prohibited-entity cost) divided by total direct cost, under IRS Notice 2026-15.

KEY FACTS

  • What is FEOC for battery storage? A set of rules that deny the 30% Section 48E credit to projects that rely too heavily on equipment from prohibited foreign entities.

  • What is the 2026 threshold? At least 55% of equipment cost must come from other suppliers, rising to 75% for projects that begin construction in 2030 and later.

  • How is it calculated? Material assistance cost ratio equals total direct cost minus prohibited-entity cost, divided by total direct cost, under IRS Notice 2026-15.

  • What happens if a project fails? It does not qualify for the credit. There is no partial credit.

  • Who is exempt from the ratio test? Projects that began construction before January 1, 2026.

What is FEOC for battery storage?

FEOC stands for foreign entity of concern. The One Big Beautiful Bill Act bars clean energy credits for projects that receive “material assistance” from a prohibited foreign entity (PFE), which is generally a company tied to China, Russia, Iran or North Korea through ownership, control or influence. For batteries the rule bites hard. A battery system is built from dozens of manufactured parts, and a large share of the world’s battery cell supply still comes from Chinese manufacturers.

The test applies to any storage project that begins construction on or after January 1, 2026. Projects that started building before that date do not have to pass the material assistance test, although separate ownership and effective control rules apply to everyone. If you are new to the credit itself, start with our guide to the Section 48E battery storage tax credit and our overview of FEOC rules for clean energy credits.

How does the 55% test work?

Treasury’s Notice 2026-15, issued in February 2026, sets out the math. The test is called the material assistance cost ratio, or MACR. You take the direct cost of every manufactured product and component in the project (A), subtract the direct cost of the ones made by prohibited foreign entities (B), and divide by A. The result must meet a minimum percentage that depends on the year construction begins.

MACR = (total direct cost − PFE direct cost) ÷ total direct cost

Energy storage faces a higher bar than solar or wind. The thresholds in 26 U.S.C. 7701(a)(52) for storage projects are:

  • 2026 construction start: 55%

  • 2027: 60%

  • 2028: 65%

  • 2029: 70%

  • 2030 and later: 75%

Solar, wind and other generation facilities start lower, at 40% in 2026, and reach 60% for 2030 and later. The rising bar is why a ratio that passes today can fail on a project that starts building two years from now. The chart below sets the threshold against the credit’s own phase-down and lets you slide in your project’s ratio to see which construction years it survives.

Construction starting 2027: share of full credit
100%Full credit
Credit available to youCredit if FEOC test passedFEOC thresholdYour ratio
0%25%50%75%100%'25'26'27'28'29'30'31'32'33'34'35'36Your ratio 68%
FEOC threshold, 202760%
Phase-out, 2027100%
Last start year with a credit2028

At 68%, projects starting after 2028 fail the material assistance test and lose the credit, even before the phase-out begins.

Sources: 26 U.S.C. 48E(e), 45Y(d)(3), 7701(a)(52). Storage placed in service with a wind or solar facility is not subject to the 2027 wind and solar cutoff.

What counts as a prohibited foreign entity component?

The test looks at manufactured products and their components, not raw materials. For a battery system, the items that count include:

  • Battery cells

  • Modules, racks and packs

  • Inverters and power conversion systems

  • Battery management and energy management systems

  • Enclosures, cooling and fire protection

  • Wiring, switchgear and other electrical equipment

Steel and iron construction materials and main power transformers sit outside the count. Two details trip people up. First, you use your own acquisition cost, not the supplier’s cost. If you buy a finished battery pack for $2 million, that is the number that goes into your math, and the supplier’s status decides which column it lands in. Second, supplier status is generally tested on the last day of the supplier’s tax year, so ask vendors for fresh certifications rather than relying on last year’s paperwork.

Control matters too. A contract can give a specified foreign entity “effective control” over a project, and the notice treats a technology license entered into or changed on or after July 4, 2025 as automatically giving that control. Treasury has left most of the detail to future regulations, so read licensing and software terms with your lawyer.

How a battery project passes the FEOC test in four steps: 1, list every part (cells, racks, inverters, enclosures, controls); 2, tag each supplier as a prohibited foreign entity or not; 3, do the math: MACR equals total cost minus prohibited-entity cost, divided by total cost; 4, beat the threshold, which rises each year from 55% to 75%.

How do you calculate your battery system’s MACR?

Start with the bill of materials. List each manufactured product and component, record what you paid, and tag each one as coming from a prohibited foreign entity or not. The notice gives you three routes: trace the actual costs, use the safe harbor tables, or rely on supplier certifications.

For battery energy storage systems, the IRS lets you reuse the 2023 to 2025 domestic content safe harbor tables (Notices 2023-38, 2024-41 and 2025-08) to identify components and assign cost percentages. Other storage technologies cannot use those tables. The notice stays in effect until Treasury issues proposed regulations and formal MACR safe harbor tables, and we have not seen those tables published yet.

Suppliers certify their status in writing, signed under penalties of perjury, and you keep those records for six years. You can generally rely on a certificate unless you have reason to know it is wrong, and penalties can apply if you ignore warning signs.

Here is a worked example with round numbers. A 100 MWh project costs about $30 million at $300 per kWh, so the 30% credit is worth up to about $9 million. Suppose cells make up 40% of the equipment cost and come from a prohibited entity, while everything else is clean. The MACR is 60%, which passes in 2026 and 2027 but fails for a project that begins construction in 2028, when the bar is 65%. Raise the cell share to 48% and the MACR drops to 52%, which fails even in 2026. Try your own mix below: flip a component to prohibited-entity sourcing and watch the bar cross the required line.

Material assistance cost ratio (MACR)
60.0%Passes · 55% required
55% non-PFE required
Hover a block to see its share of the build.
Non-PFE costPFE-sourced cost
Non-PFE share60.0%
PFE share40.0%
Max PFE share allowed45%
Margin+5.0 pts
Credit at stake (30% of installed cost, before adders)
$9.0M

Comfortable margin. Keep the certifications and cost workpapers for six years. At this mix you clear the threshold for construction starts through 2027 and miss it from 2028.

Screening tool only. MACR = (A − B) ÷ A under IRS Notice 2026-15, using the taxpayer's direct costs of manufactured products and components. Steel and iron and main power transformers are excluded, and ownership and effective control tests apply separately. Credit at stake is a rough 30% of installed cost, not a tax computation.

What happens if your battery project fails the FEOC test?

A project that misses the threshold does not qualify for the credit. There is no partial credit for a 54% result. On the example above, that is up to $9 million of value gone, plus any tax equity or transfer deal that was counting on it. Buyers of transferred credits will want proof before they pay, so a weak file can mean a lower price or no deal. Our guide to selling tax credits covers what buyers ask to see.

There is also a tail. The law carries a 10-year recapture period for certain investment credit facilities, and the IRS has not yet explained how it works in practice. If you may sell a project, read up on ITC recapture and tax credit insurance before you sign.

Interconnection gets its own test. Qualified interconnection property is measured separately, and if it falls below the threshold the facility stays eligible but that property is left out of the credit basis.

Why does FEOC matter so much for the storage boom?

Because the market is big and still building. Wood Mackenzie and the American Clean Power Association counted a record 18.9 GWh of US storage installs in the second quarter of 2026, even though power capacity slipped 7% from a year earlier to 5.4 GW. Longer-duration systems lifted energy capacity by 16%. Wood Mackenzie also withdrew its forecast of a near-term slowdown, pointing to the many projects that started construction to lock in the investment tax credit, and it now expects cumulative installations to reach 207 GW and 715 GWh by 2031. SEIA and Benchmark, which count differently, put the same quarter at 20.2 GWh.

Electrical substation with transmission equipment against an orange dusk sky, the grid connection where large battery storage projects deliver power

Almost all of that growth is utility-scale. About 17.6 GWh of the second-quarter total came from utility projects, which are the projects with the biggest credits and the most complex bills of materials. Projects that begin construction from 2026 on are the first that must prove their numbers.

18.9Total GWh
Utility-scaleResidentialCommunity, commercial and industrial
Utility-scale share93.1%
Year over year, power-8%
Year over year, energy+16%

Total power fell 7% from a year earlier to 5.4 GW, yet energy capacity rose 16% because systems are being built for longer durations.

Source: Wood Mackenzie and American Clean Power Association, US Energy Storage Monitor Q3 2026, as reported by pv magazine on October 1, 2026. SEIA and Benchmark count a different Q2 total of 20.2 GWh. Segment values are rounded.

How can developers protect the 30% credit?

  • Build the bill of materials first. List every manufactured product and component, with your acquisition cost, before you sign supply contracts.

  • Know your biggest lever. Cells are usually the largest single cost line, so a cell swap moves the ratio more than any other change.

  • Collect certifications early. Get signed supplier certificates with the required identification numbers, and keep them for six years.

  • Write the risk into contracts. Ask for representations and warranties on supplier status, and a remedy if a supplier’s status changes.

  • Leave a margin. Aim for a ratio several points above the threshold so a cost change or a reclassified part does not push you under.

  • Plan for next year’s bar. If construction might slip, remember the threshold rises 5 points a year for storage.

  • Get a second opinion. Have a tax advisor or credit insurer review the file before a buyer or lender does.

Transmission towers and power lines at sunset across open ground, the grid that growing US battery storage capacity supports

Is the 30% storage credit still worth it?

Yes, for projects that can document their supply chain. Standalone storage keeps the full credit for projects that begin construction through 2033, then steps down to 75% in 2034, 50% in 2035 and nothing after. The FEOC test does not end the credit. It raises the price of carelessness. Teams that treat the ratio as a design input, not a filing-season surprise, keep the full 30%.

Cenet Capital helps developers value the credit and sell it to corporate buyers. For cost context, see our breakdown of what a battery system really costs per kWh. Share your system size and supplier mix through our get-started form and we will show you what your credit could bring in.

Sources

Frequently Asked Questions

What is FEOC for battery storage?

FEOC stands for foreign entity of concern. For battery storage, it means a project cannot claim the Section 48E tax credit if too much of its equipment cost comes from prohibited foreign entities, which are generally companies tied to China, Russia, Iran or North Korea. The test is the material assistance cost ratio under IRS Notice 2026-15.

What is the FEOC threshold for battery storage in 2026?

Does FEOC apply to battery projects that started construction before 2026?

Can I still use Chinese batteries and get the 30% credit?

Can Cenet Capital help me with a battery storage tax credit?

Is your battery project at risk?

Cenet Capital helps storage developers and businesses value the Section 48E storage investment tax credit and sell it to corporate buyers for cash. Share your system size, supplier mix and timeline, and we'll show you what your credit could bring in and what a buyer will want to see.

Interested in selling your clean energy tax credits?

  • More Insights

Cenet Capital was founded in on a simple premise: public markets price in consensus faster than they price in research. A small team built a trading book around that idea concentrated, thesis-driven, willing to be early.

Follow Us:

Cenet Capital was founded in on a simple premise: public markets price in consensus faster than they price in research. A small team built a trading book around that idea concentrated, thesis-driven, willing to be early.

Follow Us:

Cenet Capital was founded in on a simple premise: public markets price in consensus faster than they price in research. A small team built a trading book around that idea concentrated, thesis-driven, willing to be early.

Follow Us: