Most wind farm cost figures online are years old, quoted in pounds, or about a single backyard turbine. Here are the 2026 numbers for U.S. utility-scale projects: what a wind farm costs to build, per turbine and by region, what it costs to run, and how much federal tax credits take off.

QUICK ANSWER

A U.S. wind farm cost about $2,100 per kW to build in 2025, per Berkeley Lab, or about $210 million for 100 MW. The turbines are about half of that, roughly $1,100 per kW. Regional averages ran from $1,760 in Texas to $2,840 in the Mid-Atlantic. Federal tax credits can offset a quarter to nearly half of that.

KEY FACTS

  • What does a wind farm cost per MW? About $2.1 million per MW installed for 2025 projects, or $2,100 per kW.

  • What does a commercial wind turbine cost? About $4.2 million for the turbine alone at the 3.8 MW average, and about $8 million installed.

  • What is the wind farm O&M cost? Roughly $20 to $40 per kW per year for newer projects.

  • What is the levelized cost of wind? About $52 per MWh for 2025 projects, before the production tax credit (PTC).

  • What's the 2026 wind PTC? 3.1 cents per kWh for 10 years with wage and apprenticeship rules met, or 0.6 cents without.

  • Can wind still claim the investment tax credit (ITC)? Yes, 30% under Section 48E, on the same deadlines as the PTC.

  • What's the deadline? Construction begun by July 4, 2026, or placed in service by December 31, 2027.

How much does a wind farm cost?

A U.S. wind farm cost about $2,100 per kilowatt to build in 2025, according to Berkeley Lab. A 100 MW project comes to roughly $210 million, or about $8 million for each of its 26 turbines. Regional averages ran from $1,760 per kW in Texas to $2,840 in the Mid-Atlantic.

Those figures come from the Land-Based Wind Energy Technology Data Update, 2026 Edition, which tracks installed costs for land-based projects of more than 100 kW. Installed cost covers everything needed to start selling power: turbines, foundations, roads, electrical lines, the substation and the grid connection. It doesn't include financing or the cost of running the farm, which we cover below. The cost of a wind farm scales almost in line with its size, so per-kW figures are the easiest way to compare projects.

Where a wind farm's $2,100 per kW goes: turbines are about $1,100 per kW and everything else, including foundations, roads, cabling, substation, grid connection and development, is about $1,000 per kW. That's $210 million for a 100 MW wind farm, 26 turbines at the 2025 average of 3.8 MW, and about $8 million installed cost per turbine. Source: Berkeley Lab.

How much does one wind turbine cost?

The turbine itself costs about $1,100 per kW, or roughly $4.2 million for the 3.8 MW average turbine installed in 2025. Built into a project, with its share of foundations, roads and grid work, each turbine comes to about $8 million. Turbines make up only about half of a wind farm's cost.

Turbines have grown fast. The 2025 average had a 102-meter hub height and a 141-meter rotor, per Berkeley Lab. Their price hasn’t followed. Turbine prices topped $2,000 per kW around 2008 and have held near $1,000 to $1,200 since 2017. Owners who swap blades and nacelles on an old project, known as partial repowering, have spent about $1,180 per kW on average. Put another way, the wind turbine cost per MW is about $1.1 million for the machine and about $2.1 million once it’s built into a project.

Why do wind farm costs vary so much by region?

Building in Texas costs about 40% less than in the Mid-Atlantic. Berkeley Lab put 2024 and 2025 projects in ERCOT at $1,760 per kW and in PJM at $2,840. Bigger projects, flatter land, cheaper labor and simpler grid connections all push costs down.

Wind farm cost by region for 2024 and 2025 projects, per kW: ERCOT in Texas $1,760, West about $1,900, SPP about $1,950, MISO about $2,250 and PJM in the Mid-Atlantic $2,840, against a U.S. average of $2,100. Source: Berkeley Lab.

The gap carries through to the price of power. Berkeley Lab estimates a levelized cost of energy of about $45 per MWh for recent ERCOT projects and more than $90 in PJM, before tax credits. A project's location also decides whether it can claim the 10% energy community bonus, which our guide to ITC adders explains.

What does a wind farm cost after tax credits?

Federal credits can offset a quarter to nearly half of the cost. In 2026, the 45Y Production Tax Credit (PTC) pays 3.1 cents per kWh for 10 years. A 100 MW farm at a 37% capacity factor could earn about $100 million. The Investment Tax Credit (ITC) is 30% of eligible cost instead.

Both rates assume the project meets the wage and apprenticeship rules or is under 1 MW AC. Without them, the credit drops to one-fifth. Form 7220 is where you prove compliance. Most wind owners pick the PTC because their capacity factors are high, as our ITC vs. PTC comparison shows. Many sell the credit for cash: PTCs averaged 93 cents per dollar in 2026, Crux reports. Run your own project below.

Here's how the math works on a typical project. A 100 MW farm in the Midwest at about $2,250 per kW costs roughly $225 million. At a 37% capacity factor, it produces about 324,000 MWh a year. Ten years of PTCs at 3.1 cents come to about $100 million, and selling them at 93 cents brings in about $93 million. That's before discounting for the 10-year wait, which tax equity investors and credit buyers price in. Even so, the credit can be worth more than 40% of what the project cost to build.

Estimated installed cost
$210.0M$2,100 per kW
Installed cost$210.0M
10-year PTC (nominal)$100.5M
Cash if the credit is sold$93.4M
Turbines at 3.8 MW26
Cost per turbine$8.1M
Power per year324,120 MWh
O&M per year$3.0M
Credit per MWh$31

At 3.1 cents per kWh for 10 years, the PTC is worth about $100.5M, or $93.4M in cash if sold. Only projects that began construction by July 4, 2026, or are in service by the end of 2027 can claim it.

Illustrative. Costs are 2024-2025 averages from Berkeley Lab; non-labeled regions are read from its chart. The ITC assumes 90% of cost is eligible. PTC uses the 2026 rate with no inflation adjustment and no curtailment. O&M uses $30 per kW-year.

How much does it cost to run a wind farm each year?

Newer wind projects report operations and maintenance costs of roughly $20 to $40 per kW per year, or about $2 million to $4 million for a 100 MW farm. Spread over its lifetime output, a project built in 2025 produces power for about $52 per MWh before tax credits.

Berkeley Lab notes its O&M sample is limited and doesn't capture every operating cost. Land leases, insurance and property taxes add to the yearly bill. Output drives the rest of the math. Projects built in 2024 ran at a 37.1% capacity factor in 2025, while the whole fleet averaged 34%.

Aerial view of wind turbines along a ridge with a winding access road at sunset

Curtailment, when the grid can't take the power, also eats into revenue. It was highest in the Southwest Power Pool, at 9% of potential wind output in 2025.

Why have wind farm costs gone up since 2022?

Installed costs bottomed out near $1,600 per kW for 2022 projects and climbed to $2,100 by 2025. Turbine prices stayed close to $1,100 over that time, so the increase came from the rest of the project. The levelized cost rose from $40 to $52 per MWh.

Berkeley Lab cautions that cost data for 2024 and 2025 projects is still preliminary. Even so, today's costs are well below the 2009 and 2010 peak of about $3,000 per kW. Drag across the chart to compare any year.

Installed cost per kW, 2025 projects
$2,100Turbines $1,100
$0$1,000$2,000$3,0002008201120142017202020232025
Installed project costTurbine price

In 2025, the average project cost about $2,100 per kW, and turbines alone about $1,100. Turbine prices have barely moved since 2017, so most of the rise after 2022 came from the rest of the project.

2025 average$2,100/kW
2022 low~$1,600/kW
Turbine share, 2025About half

Source: Berkeley Lab, Land-Based Wind Energy Technology Data Update, 2026 Edition, in 2025 dollars. Cost and turbine values before 2025 are read from its charts and rounded.

Can a new wind farm still get federal tax credits?

Only on a deadline. Under the One Big Beautiful Bill Act, wind projects that began construction by July 4, 2026, keep their path to the 45Y and 48E credits. Projects that started later must be placed in service by December 31, 2027. After that, new wind farms get no federal credit.

The cutoff is in Section 45Y(d) and the matching rule in Section 48E. Projects that started in time still have to show continuous work, and foreign-entity rules apply to construction starting in 2026, as our FEOC guide explains. A federal court vacated the stricter beginning-of-construction test in June 2026; see our Notice 2025-42 update. Our wind production tax credit guide covers the full rate history.

How do wind farms make money?

Mostly by selling power under long-term contracts. LevelTen put the average wind power purchase agreement at $83.79 per MWh in the second quarter of 2026, up 17.5% from a year earlier. Tax credits, sold or used, add the rest. Without a contract, wholesale prices are much lower.

Berkeley Lab valued wind power on the wholesale market at $15 per MWh in the Southwest Power Pool and $69 in New England in 2025. That spread is why most developers line up an offtake agreement before they build. LevelTen's figures come via pv magazine USA. Developers without enough tax appetite either bring in tax equity investors or sell the credits to corporate buyers.

Sources

Frequently Asked Questions

How much does a 1 MW wind turbine cost?

At 2025 averages, about $1.1 million for the turbine and about $2.1 million installed. New utility-scale turbines are much bigger, averaging 3.8 MW, and smaller turbines usually cost more per kW.

How many homes can a 100 MW wind farm power?

Is the PTC or the ITC better for a wind farm?

Does Notice 2025-42 still apply to wind projects?

Can Cenet Capital help with wind tax credits?

Building or buying into a wind farm?

Cenet Capital helps wind developers and owners value their production or investment tax credits, check them against the 2026 and 2027 deadlines and sell them for cash. Share your project size, location and construction status, and we'll show you what your credits could bring in.

Interested in selling your clean energy tax credits?

  • More Insights

Cenet Capital was founded in on a simple premise: public markets price in consensus faster than they price in research. A small team built a trading book around that idea concentrated, thesis-driven, willing to be early.

Follow Us:

Cenet Capital was founded in on a simple premise: public markets price in consensus faster than they price in research. A small team built a trading book around that idea concentrated, thesis-driven, willing to be early.

Follow Us:

Cenet Capital was founded in on a simple premise: public markets price in consensus faster than they price in research. A small team built a trading book around that idea concentrated, thesis-driven, willing to be early.

Follow Us: